Secondary School Complex
Welcome to the Elizabethtown Area Middle School and Elizabethtown Area High School Building Project webpage! We are excited to share our vision for the future of education in our community. At Elizabethtown Area School District, we are committed to fostering an environment that empowers students to thrive academically, socially, and emotionally. As part of this dedication, we are pleased to present our plans for a potential new building project. You can find more information by exploring the resources published below.
Project Updates
September 16, 2025
Informational Session w/ Q&A Hosted by RLPS – Tuesday, September 16, from 6–8 PM, including an opportunity for public comment specifically regarding the secondary school complex project. Please note: a previous handout incorrectly listed the date as September 19; the correct date is September 16.
September 9, 2025
During the regularly scheduled board meeting on September 9, 2025, the Elizabethtown Area School District Board of School Directors received an update from RLPS Architects on the status of the feasibility study.
August 19, 2025
The Elizabethtown Area School District invited community members to participate in guided tours of the middle and high school buildings on Tuesday, August 19, 2025. These tours offered an important opportunity for residents - whether or not they have children currently enrolled in the District - to explore key areas of the secondary school complex that are in need of renovation and repair.
May 19, 2025
RLPS Architects held a public Town Hall meeting on May 19, 2025, in the Elizabethtown Area Middle School auditorium. The meeting was open to the entire community.
- Presentation
- Town Hall Recording
- Community Survey (Open May 21 through June 5)
May 13, 2025
During the regularly scheduled board meeting on May 13, 2025, the Elizabethtown Area School District Board of School Directors received an update from RLPS Architects on the status of the feasibility study.
March 25, 2025
During the regularly scheduled board meeting on March 25, 2025, the Elizabethtown Area School District Board of School Directors approved a request from RLPS Architects to add a student count survey to their Feasibility Study at a cost of $5,000.
March 11, 2025
During the regularly scheduled board meeting on March 11, 2025, the Elizabethtown Area School District Board of School Directors discussed a request from RLPS Architects to add a student count survey to their Feasibility Study at a cost of $5,000.
January 28, 2025
During the regularly scheduled board meeting on January 28, 2025, the Elizabethtown Area School District Board of School Directors approved RLPS Architects to conduct a second review of the High School/Middle School complex.
January 14, 2025
During the regularly scheduled board meeting on January 14, 2025, the Elizabethtown Area School District Board of School Directors discussed a second architect review of the High School/Middle School complex by a different architect.
December 3, 2024
During the regularly scheduled board meeting on December 3, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #3 on the implications of the recently conducted feasibility study.
November 12, 2024
During the regularly scheduled board meeting on November 12, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #2 on the implications of the recently conducted feasibility study.
October 8, 2024
During the regularly scheduled board meeting on October 8, 2024, the Elizabethtown Area School District Board of School Directors viewed presentation #1 on the implications of the recently conducted feasibility study.
September 12, 2024
In Focus article published providing clarity on the current status of the EAMS/EAHS Building project.
September 10, 2024
During the regularly scheduled board meeting on September 10, 2024, representatives from Crabtree, Rohrbaugh & Associates, the District’s architectural firm, presented their findings from a nearly year-long feasibility study.
September 26, 2023
During the regularly scheduled board meeting on September 26, 2023, the Board of School Directors authorized Crabtree, Rohrbaugh & Associates to complete a Feasibility study of all District facilities. This study will become part of the District's 5-year plan. There is no charge for this study.
September 12, 2023
During the regularly scheduled board meeting on September 12, 2023, the Board of School Directors discussed approval of Crabtree, Rohrbaugh & Associates Architects to complete a Feasibility study of all District facilities.
